August 27, 2014

The CarMax site in Raliegh is progressing quickly and is on schedule to be complete in October. Crews have completed much of the critical utilities and mass excavations.  Final grading activities are now underway.

July 2, 2014

Crews began installing the large underground detention system at CarMax in Raleigh yesterday.  The team was excited to get this installation started.  The system is comprised of 2,000 linear feet of 84" corrugated metal pipe.  This equates to almost 68,000 cubic feet a...

May 13, 2014

Wells Brothers has recently mobilized at a proposed CarMax facility in northern Raleigh.  This will be a challenging project, due to its fast-track schedule.  Crews will move over 80,000 cy of dirt, place 18,000 tons of aggregates, bury 8,000 feet of pipe, and construc...